Skip to main content
Technical Resource

Transformer Loading & Unloading: Method Statement

Step-by-step procedures for safe loading, transport and unloading of power transformers at EHV substation sites — covering T&P requirements, crane placement, rigging, barricading and site unloading.

📅 Updated: January 2024⏱ 5 min read🔌 Covers: Power Transformer · EHV Substation · GIS Projects

Introduction

This Method Statement describes the safe sequence of work for loading and unloading power transformers at stores and EHV substation sites. Power transformers are high-value, precision-engineered items — improper handling can cause winding damage or bushing breakage that may not be immediately visible but can result in failure once energised.

All operations must be carried out under the continuous supervision of an experienced Site Engineer and Safety Engineer. Only authorised personnel are permitted inside the work area during any lift.

ScopeThis Method Statement covers loading at the store, road transport and unloading onto the transformer foundation at site. It includes all T&P requirements, crane and trailer placement, rigging, barricading and safety precautions.

Sequence of Activities

All transformer loading and unloading operations follow this sequence without exception:

Material / Tools & Plants Required
Arrange Crane and Trailer
Availability of T&P Test Certificates
Placement of Crane and Trailer
Barricading of Crane, Trailer and Loading Area
Lifting of Transformer
Placement on Trailer
Transportation to Site
Unloading on Foundation at Site

Material & T&P Required

All lifting equipment must carry valid third-party test certificates, which must be available at site before work commences.

#Equipment / MaterialRemarks
1D ShackleRated SWL — one per lifting point
2Chain BlockFor controlled lowering and positioning
3SlingsSteel wire rope or webbing; rated for transformer weight
4CraneAppropriate capacity — verified against transformer weight including rigging
5JackAppropriate capacity for the transformer weight
6Wooden Sleepers / BlocksFor wheel chocking and base packing on trailer
7U ClampFor securing slings and rigging connections
8Double PulleyFor mechanical advantage when manoeuvring
9Ring & D-Spanner SetGeneral rigging and fastening
10Screw Driver SetAs required
11Ratchet SetAs required
12Adjustable SpannerAs required
13PlierAs required
14Wire CutterAs required
15RopeFor guiding and steadying the transformer during lifts

Loading Procedure

  • Position the crane adjacent to the transformer at the store. Confirm ground is suitable for crane outrigger loads.
  • Block all wheels of the crane and trailer — both front and rear — with wooden sleepers before any lifting begins.
  • Place crane jacks on firm ground and extend to working position.
  • Tie all four sides of the transformer with rope to allow controlled guiding during the lift.
  • Attach slings to the transformer lifting hooks using D-Shackles, following the manufacturer's rigging arrangement.
  • Lift the transformer slowly and steadily onto the trailer. A qualified Rigger and Banksman must guide the crane operator throughout — no sudden movements at any stage.
  • Load transformer accessories onto a separate trailer and secure with chain or rope.
  • Secure the transformer on the trailer using chain or rope — verify all lashings are tight before the vehicle moves.

Transportation to Site

  • Before departure, verify the approved transport route for height restrictions, bridge load limits and road width constraints.
  • Maintain low, constant speed throughout the journey. Avoid sharp braking, acceleration and tight turns.
  • Check all lashings on arrival at site before commencing unloading.

Unloading Procedure — Site

  • Position crane and trailer at the designated unloading area adjacent to the transformer foundation. Confirm the ground is level and stable for crane outriggers.
  • Block all crane and trailer wheels with wooden sleepers — front and rear.
  • Place crane jacks and extend to working position.
  • Tie all four sides of the transformer with rope before lifting begins.
  • Barricade the entire unloading area with warning tape. No unauthorised personnel are permitted inside the barricade at any time.
  • Use the same T&P as used for loading — confirm all test certificates remain valid.
  • Lift the transformer clear of the trailer and lower slowly onto the prepared foundation.
  • Fix transformer wheels / anchor bolts to the foundation as required.
  • Unload accessories from the second trailer and place as directed by the Site Engineer.
  • Site Engineer and Safety Engineer must monitor all operations continuously throughout loading and unloading.
EHV Substation Projects — KVPEKVPE provides EPC services and project management for EHV substation construction across India, including transformer erection, cable laying and commissioning. Contact the Projects Team →

Safety Requirements

📋

All T&P third-party test certificates must be valid and available at site before work starts

🚧

Barricading with warning tape is mandatory at loading and unloading areas — no unauthorised access

🪵

Wheel chocking required for all crane and trailer wheels (front and rear) before any lifting begins

🪢

All four sides of the transformer must be tied with rope to allow controlled guiding during the lift

👷

Experienced Site Engineer and Safety Engineer must be present and monitoring throughout all operations

🏗️

Crane capacity must be verified against transformer weight before selection — do not underestimate rigging weight

D-Shackles must be rated to SWL and correctly pinned — inspect before each use

🔍

Inspect transformer bushings and fittings after unloading — report any damage before proceeding to erection

Substation Projects

Planning an EHV Substation or Transformer Installation?

KVPE provides EPC services for GIS and AIS substations from 33 kV to 400 kV across India — including transformer erection, cable laying and commissioning.

Get in Touch →