Skip to main content
Technical Resource

Cable Drum Loading & Unloading: Method Statement

Safe work execution procedures for loading 66 kV cable drums onto trailers at centralised stores and unloading at cable laying sites — covering crane selection, rigging, transport and site barricading.

📅 Updated: December 2025⏱ 5 min read🔌 Covers: 66 kV · HV Cable Drum Handling

Introduction

This Method Statement covers the loading and unloading of cable drums for 66 kV underground cable laying works. It defines safe work execution procedures for moving cable drums from a centralised store onto trailers and transporting them to the cable laying site.

Cable drums for EHV projects are heavy and fragile — improper handling can cause sheath damage or internal conductor deformation that may not be visible but can lead to failure under high voltage. All operations must be carried out under the supervision of an experienced Site Engineer and Safety Engineer.

ScopeThis document defines safe methodologies for cable drum loading and unloading. It shall be referred to during execution and covers all T&P, crane requirements, rigging procedures and unloading at site.

Sequence of Activities

All loading and unloading operations follow this sequence without exception:

Arrange Materials, Tools & Plants required for Loading
Arrange Appropriate Capacity Crane and Trailer
Confirm T&P Test Certificates are available at site
Position Crane & Trailer at Centralised Store Location
Lift Cable Drums using Crane
Place Cable Drums on Trailer — secure with Chain/Rope
Transport Cable Drums from Store to Cable Laying Site
Barricade the Unloading Area at Site
Unload Cable Drums at Site of Cable Laying

Material & Equipment Required

The following tools, plants and materials are required for all loading and unloading operations. Third-party test certificates must be available at site for all T&P during operations.

#Equipment / MaterialPurposeSpecification
1CraneLifting cable drumsAppropriate capacity for drum weight
2TrailerTransporting cable drumsAppropriate load capacity
3D ShackleRigging connectionRated for drum weight
4Chain BlockControlled liftingAppropriate capacity
5SlingsSecuring drum to crane hookAppropriate capacity for drum weight
6Hydraulic JackRaising drum for spindle insertionAppropriate capacity for drum weight
7Wooden BlocksWheel chocking — crane & trailerFront & rear wheels both sides
8Chain / RopeSecuring drum on trailer; drum tie-up before liftingRated for drum weight
9Miscellaneous Hand ToolsGeneral rigging & securingAs required

Loading Procedure — Store to Trailer

  • Arrange a crane of appropriate capacity for the drum weight and position it at the centralised cable drum store.
  • Block all front and rear wheels of both the crane and trailer with wooden blocks before any lifting begins.
  • Tie up each cable drum with rope before attaching slings to prevent rotation during lift.
  • Attach slings of appropriate capacity around the cable drum flanges. Connect to crane hook via D-shackle.
  • Lift the cable drum slowly and steadily — no sudden movements. A banksman must guide the crane operator throughout.
  • Lower the drum onto the trailer bed with care — ensure the drum sits stable and does not roll.
  • Secure each cable drum on the trailer tightly using chain and/or rope before moving.
  • Verify all securing is firm before the trailer departs the store.

Transportation to Site

  • Trailers will transport cable drums from the centralised store to the site of cable laying.
  • Route must be planned in advance — check for low bridges, restricted roads and overhead cables on route.
  • Speed must be kept low and constant. No sharp braking or acceleration with cable drums loaded.
  • Drum securing must be checked at the start of journey and re-verified at site before unloading.

Unloading Procedure — Site of Cable Laying

  • Position the trailer and crane safely near the designated unloading area at the cable laying site.
  • Barricade the unloading area completely before any lifting begins. No unauthorised personnel within the barricaded zone.
  • Block all crane and trailer wheels with wooden blocks.
  • The same T&P used for loading shall be used for unloading — no substitution without approval.
  • Lift each cable drum slowly from the trailer bed using the crane.
  • Lower the drum to the designated drum storage location at site. Fix drums in position using wooden blocks to prevent rolling.
  • Experienced Site Engineers and Safety Engineers must continuously monitor all operations.
Equipment Hire — KVPEKVPE provides cable drum jacks, slings, and cable pulling equipment on hire for 66 kV–400 kV projects across India. View available equipment →

Safety Requirements

📋

All T&P third-party test certificates must be available at site before work starts

🚧

Barricading mandatory at unloading area — no unauthorised access during operations

🪵

Wheel chocking required for all crane and trailer wheels at all times during lifting

👷

Experienced Site Engineer and Safety Engineer must supervise all loading/unloading

🔗

Slings must be rated for cable drum weight — check and confirm before each lift

🔍

Inspect cable drum end caps and seals after unloading — replace any that are damaged

Equipment Hire

Planning a 66 kV or EHV Cable Project?

KVPE provides winch machines, cable drum jacks, slings and complete cable laying services on hire for 66 kV–400 kV projects across India.

View Equipment Hire →